 Kolam Olakan di Jelambar Sudah 60 Persen
....
photo Rudi Hermawan - Beritajakarta.id

Stilling Basin Construction in Jelambar Reaches 60 Percent

The progress of stilling basin construction work on Jalan Satria Raya, Jelambar, Grogol Petamburan which carried out by West Jakarta Water Resources (SDA) Sub-agency has reached 60 percent.

We build this stilling basin to minimize inundation in Jelambar Urban Village

Grogol Petamburan SDA Unit Head, Agus conveyed, this stilling basin with length 5.5 meters, width 1.5 meters, and height 3 meters is expected to accommodate water with volume up to 25 qubic meters.

"We build this stilling basin to minimize inundation in Jelambar Urban Village," he explained, Friday (11/20).

SDA Accelerates Stilling Basins Construction in Kelapa Gading

For the construction, his side deployed 25 personnel from Grogol Petamburan SDA Unit.

Anticipating inundation and flood in the area, his side not only built stilling basin, but also prepared water pump that can drain the water to Grogol River.

"We estimate to finish building this stilling basin by the end of November," he stated.

Linked News
Popular News indeks
  1. Survivors of Collapsed Houses in Malaka Jaya Receive Social Assistance

    access_time30-01-2025 remove_red_eye2207 personNurito
  2. Logistics Aid for Jakarta Flood Victims Keeps Being Distributed

    access_time30-01-2025 remove_red_eye982 personAldi Geri Lumban Tobing
  3. City Council Chairman Supports City Government Optimizing Assistance for Rorotan Farmers

    access_time30-01-2025 remove_red_eye675 personDessy Suciati
  4. N. Jakarta Vice Mayor Distributes Assistance to Flood Survivors in Sukapura

    access_time30-01-2025 remove_red_eye480 personAnita Karyati
  5. Rain Brings Excitement to Rawa Belong Milkfish Festival 2025

    access_time28-01-2025 remove_red_eye450 personFolmer